Mining, Metallurgy
On-site utility networks of the Northern industrial site of the Uvalnaya Mine, JSC “UK Sibirskaya”, Novokuznetsk: installation of heat supply networks
Read more
Client:
JSC "UK Sibirskaya"
Description of work
During the execution of work, our specialists refined and introduced additional engineering and technical changes to the design and estimate documentation in order to optimize and improve the construction of this facility.
The work was carried out on the Northern industrial site according to the Customer's working documentation. All work was completed on time with good quality, with the signing of a technical readiness certificate and the transfer of a complete set of as-built documentation.
The total length of the heating main from the Boiler House building to the Heater Building is 603.4 m, consisting of pre-insulated pipelines 325/500 with underground channels and three above-ground compensators.
Implementation period: July–November 2025.